>>>NF-A (PS-4) Topsides Upgrade for Qatar Petroleum
NF-A (PS-4) Topsides Upgrade for Qatar Petroleum 2017-11-07T14:56:18+03:30

Project Description

Project Name

NF-A (PS-4) Topsides Upgrade for Qatar Petroleum

Type Of Work

Design, detailed engineering, Procurement, Onshore construction, Load-Out, Transportation, Offshore Installation, Testing, Pre-Commissioning and Commissioning Assistance, Demolition of the Existing Systems to the Extend

Specified

Riser Treatment Platform, Utilities Platform, Flare Platform

Year

2000 (Finished), 2004-2006 (Upgraded)

Client

Petronas

Location

Malaysia

Status

Finished